Decommissioning, Closure, and Abandonment of Dams at Energy Projects

Release Date

On December 11, 2018, Alberta Environment and Parks (AEP) updated the Water (Ministerial) Regulation. This update included the release of the new Alberta Dam and Canal Safety Directive, which contains requirements applicable to the entire life cycle of a dam. The directive outlines requirements for dam owners for dams, including

  • the use of qualified professionals and qualified individuals;
  • dam consequence classifications;
  • the use of risk assessments;
  • how to design, construct, and operate;
  • required submissions for approval/authorization and dam safety reporting;
  • dam safety and emergency management; and
  • decommissioning, closure, and abandonment.

This manual should be read in conjunction with the regulation and the directive. This manual focuses exclusively on section 9 of the directive, which deals with the end of a dam’s life (decommissioning, closure, and abandonment). It is intended to guide both dam owners and AER reviewers through the application of the directive’s decommissioning, closure, and abandonment requirements to dams regulated by the AER. This manual and the directive do not address custodial transfer while managing
hazards and risks to reasonably practicable levels.

This manual only supplements the regulation and directive. The reader should be familiar with any other legislation, rules, regulations, directives, codes, and directions that may apply to closure, decommissioning, reclamation, and abandonment.

When a dam that stores water (or water containing other substances) reaches the end of active service, in order to properly abandon it, the directive requires that it be breached or fully removed (decommissioned) and not be capable of storing water in the future.

The physical “closure” of a tailings facility with dams is a more complex process, and for tailings dams, the manual provides additional guidance.

The manual is organized as follows:

  • Section 2 gives a brief description of decommissioning and abandonment for water dams.
  • Section 3 provides guidance for tailings dams on reducing risk.
  • Section 4 provides guidance for designing for closure and abandonment of tailings dams.
  • Section 5 describes and illustrates the regulatory process for receiving and authorizing dam decommissioning, closure, and abandonment submissions.